SAP Calendar


[ Follow Ups ] [ Post Followup ] [ Message Board ]

Posted by [IP Address: 12.28.164.2] 'Wayne' on September 14, 2001 at 12:16:18 EST:

I have a question about trasporting the SAP calendar from Dev to PRD. I created a new factory calendar in DEV and want to transport it to QA and PRD. When I select the transport button I get a message saying that all calendars will first be deleted and then replaced. The first question is "is there any way to transport just the calendar I created or do I have to transport them all?". The second question is " If I have to transport all the calendars how does this affect the current applications and jobs that are scheduled using the calendars, will these jobs have to be reschedule using the new calendars or will the jobs be OK and get the calendar information at the time they run. Again I only created one new calendar all the other calendars should be the same.

Thanks.


Follow Ups:



Post a Followup


Name:
E-Mail:
Subject:

Message:


[ Follow Ups ] [ Post Followup ] [ Message Board ]