Posted by [IP Address: 192.83.224.17] 'marty' on July 16, 2001 at 19:53:54 EST:
My customer met with SAP reps from Waldorf this week to discuss R/2 to R/3 migration (a long-term strategy). In the short-term, we're meant to be upgrading 50F to 60J before the end of the year.
During the presentation SAP presented a slide which showed that, of the 600+ R/2 customers remaining, there were only 2 on 6.0J, while 5.0J had over 50 customers.
Should we continue towards a 6.0J implementation, or a 5.0J implementation ?
1. What additional frunctionality so we get in 6.0J that is not in 5.0J ?
2. Are we likely to make use of the functionality, given that we currently have no performance issues ?
3. What is the additional cost of implementing 6.0J over and above 5.0J ?
4. What impact on the project schedule would it have if we were to upgrade to 5.0J and not 6.0J ?