Example
in the material master ZZZ
lot-size for in-house production
setup time is 1 day
iteroperatioan is 1 day
process 5 days
and the base quantity is 100
when i create sales order
material ZZZ qty 200
the proposed date from availability chek is 7 days.
it doesn't count the base qty.
if for 100 the required time is 7 days then for 200 it should multiply by 2 right ?
is there anything i miss in configuration ?
is anyone could help ?
thanks in advance