Posted by [IP Address: 61.1.71.87] 'Ashish' on September 15, 2001 at 08:36:00 EST:
In Reply to: Preventive Maint Plans. posted by [IP Address: 61.1.71.87] 'sriram' on September 15, 2001 at 04:35:19 EST:
hi
it appears you are not using ip30, deadline monitoring (as it appears from you post of order auto generation). it is not required to do a long term scheduling of plans as ip30 automatically does the scheduling and calling od due calls.
try ip 30 and if required you can write to me for details or go through the sap help docs.
: hi
: i want to schedule the maintenance plans for 5 years.but in scheduling parameters,we can enter only 999 as max no days.
: is it possible to increase the field width, thru customisation / ABAP
: pl guide