Hi,

When i schedule a maint plan, i have to save it to create a order . what i want is to create an order without saving the plan everytime.
i.e if i schedule the maint plan & save it once than the orders should be created on the due date as per the call horizon.
How to do it, pl. tell me.

Thanks in advance

Chanda
Posts: 184
Joined: Thu Apr 17, 2003 3:52 am
Location: India
Contact:

Post by Chanda » Thu Jun 12, 2003 6:23 am

hi,
you have to schedule the plan only once (IP10) giving the start date..therafter the orders will be generated by the system when the call horizon is reached.
you can also use Deadline monitoring (IP30) for calling all the due maintenance plans. The system schedules the plans automatically.
Chanda

Santhosh

Post by Santhosh » Thu Jun 12, 2003 8:50 am

Hi,

You can also create a background job for executing IP30 using the T. Code SM36. So, once in a day all the plans which are defined in the IP30 variant will be scheduled.

Regards

Santhosh