I have a following business requirement.

I need to generate messages (ME92F - Monitor Order acknowledgment) where I didn't receive order acknowledgment from vendor within 3 days from PO date.

E.g.
Suppose If I create a PO on Monday, acknowledgment has to receive by Thursday.

If I didn't receive acknowledgment from vendor, then I need to send a letter to vendor for acknowledgment.

For this I have activated "Confirmation Control Keys" and then 'Monitoring' field is set to "3" and 'Ref Date' field is set to "PO date Plus monitoring time".

But when I run ME92F on Monday after the PO is issued, system pick up the PO. I don't want system to pick it up until Friday.

Is this business requirement is possible to configured through standard SAP? If not what is the alternative method?

Thanks in advance.

yoyoyo
 
Posts: 17
Joined: Mon Jul 09, 2012 10:52 am

Re: ME92F can't exclude POs by PO date (Reference Date)

Postby yoyoyo » Fri Aug 10, 2012 2:37 am

Are there anybody who can help me about this topic?

Is it not possible by ME92F?
yoyoyo
 
Posts: 17
Joined: Mon Jul 09, 2012 10:52 am

Re: ME92F can't exclude POs by PO date (Reference Date)

Postby Ha Tran » Fri Aug 10, 2012 3:58 am

Hi,

What is the ''Reference Date'' did you enter into your ME92F? What was the first urging message (expediter) value have you set in your PO?

Cheers,
HT
Ha Tran
 
Posts: 27880
Joined: Sun Mar 30, 2003 8:29 pm
Location: Perth, Western Australia

Re: ME92F can't exclude POs by PO date (Reference Date)

Postby yoyoyo » Mon Aug 13, 2012 10:04 pm

Hi,

''Reference Date'' in ME92F is Aug 14.
The first urging message (expediter) value of the PO is "2".

The document date of the PO is Aug 14.
The delivery date of the PO is Sep 10.

In my understanding, ME92F doesn't use urging message (expediter) value of the PO but ME91F use it.
ME92F uses the setting in "Set Up Confirmation Control" in customizing.
Am I correct?

Best Regards.
Yo
yoyoyo
 
Posts: 17
Joined: Mon Jul 09, 2012 10:52 am

Re: ME92F can't exclude POs by PO date (Reference Date)

Postby Ha Tran » Tue Aug 14, 2012 4:00 am

Hi,

First of all, in both ME91F (which is used to expedite the urging letter/reminder) and ME92F (which is used to expedite the PO acknowledgment) the reference date is used. Secondly, it is correct that ME92F will look into the setting of confirmation control configuration to decide when the order acknowledgment reminder letter shall be generated. If your PO document date is Aug 14 and the PO acknowledgement shall take place within 3 days since PO transmission, then ME92F won't pick up your PO till after Aug. 17. Isn't it happening in your system?

Cheers,
HT
Ha Tran
 
Posts: 27880
Joined: Sun Mar 30, 2003 8:29 pm
Location: Perth, Western Australia

Re: ME92F can't exclude POs by PO date (Reference Date)

Postby yoyoyo » Tue Aug 14, 2012 4:30 am

Hi,

My understanding seems to be the same as you. ME92F won't pick up your PO till after Aug. 17 but ME92F picks it up today...

Best Regards,
Yo
yoyoyo
 
Posts: 17
Joined: Mon Jul 09, 2012 10:52 am

Re: ME92F can't exclude POs by PO date (Reference Date)

Postby Ha Tran » Thu Aug 16, 2012 12:42 am

Hi,

If this is the case, I would suggest you to log a new OSS Message to SAP for their detailed investigation.

Cheers,
HT
Ha Tran
 
Posts: 27880
Joined: Sun Mar 30, 2003 8:29 pm
Location: Perth, Western Australia


Return to Logistics MM

Who is online

Users browsing this forum: No registered users and 8 guests




This website is not affiliated with, sponsored by, or approved by SAP AG.