Restrict changes to PO created frm Preq for network activity

Logistics : MM and its sub-modules (WM, IM, PO, LIS)

Moderators: thx4allthefish, Snowy, Ha Tran, svetja

Restrict changes to PO created frm Preq for network activity

Postby Jef » Thu Oct 31, 2002 9:30 am

Purchase requisitions are created automatically for components in network activities (Project Systems).
This company wants that it's impossible to change the component data (description, quantity, price, vendor, ... as entered in the network activity) in the PO created with reference to this purchase requisition.
When they look at the components in the network activity, they want to be sure that this equals what has been ordered.
Any ideas where to start?
How much time would it take to set it up like this?

Jef
 
Posts: 83
Joined: Thu Oct 31, 2002 8:14 am

Return to Logistics MM

Who is online

Users browsing this forum: Google [Bot] and 12 guests




This website is not affiliated with, sponsored by, or approved by SAP AG.