Post by suresap » Wed Dec 04, 2002 6:27 am

Hi All,

I am a MM consultant and am trying to explore the integration areas in PS. Can someone of u pl. help in listing the MM-PS intergrations, so that I can learn only that part of PS topics (and of course necessary topic thereof like masters, org. structure)

Thanks in advance.

Bobo
Posts: 49
Joined: Wed Nov 13, 2002 4:35 am

Post by Bobo » Thu Dec 05, 2002 1:21 am

Material item can be assigned to an activity in a project as component. This assignment triggers the creation of reservation/PR in MM. Just like assigning a material to BOM, you also have to specify the quantity needed and the requirement date, if a material is to be backflush, if it is a bulk material.

suresap
Posts: 56
Joined: Fri Oct 25, 2002 7:32 am

Thanks BoBo

Post by suresap » Tue Dec 10, 2002 1:50 am

Thanks Bobo

Saphir

Post by Saphir » Tue Dec 17, 2002 8:02 am

Network activities of type 'external processing' can automatically generate purchase requisitions. That is, for sub-contracting or external service procurement (consulting etc.). All the purchasing data can be determined via info records which are inserted in o.m. activities.