Float time while running cycle counting document by Job

Logistics : MM and its sub-modules (WM, IM, PO, LIS)

Moderators: Snowy, thx4allthefish, Ha Tran, svetja

Post Reply
Anandj
Posts: 211
Joined: Thu Jul 29, 2004 10:03 am

Float time while running cycle counting document by Job

Post by Anandj » Mon Dec 05, 2016 7:49 pm

Hello ,
I am confused with how the float time i when running RM07ICN1 through background job .Suppose the float time for
cycle count indicator A (12 times a fiscal year)is defined as 5 days . Assuming if the batch job runs once in day for the plant and if the PI gets
document created on the first due day itself , then there is no use real use for floats days ? Background job is going create the PI document on its
proposed date and hence I am not sure how this float days will influence the grace period .

Thanks in Advance for your immediate response .

with regards ,
AnandJ