Hi Gurus,
we are facing Problems, when we compete an Inspection Lot, Origin 14 with Usage Decision OK and Standard-follow-up Action QM_PM. This will set the Order status to TECO, but the completion date is not the Usage Decision date, but the planned finish date on the Order.
To have a proper planning, we need the Usage Decision date as completion date. This happens on different settings in Maintenance Plan, time-based, key-date based, always the same Result.
Does anybody know, if there is a Customizing- or Master data setting, which transfers the Usage Decision date as completion date?
Many thanks for your ideas, regards
Paul