Post by manianz » Sat Jun 06, 2015 11:54 am

Hello Experts

When only the Task is released [NOT the header Request] from DEV and imported into QA system, is there a way to check whether the Tasks were imported? [If the Request is released, I can check the log]

Zavaros
Posts: 757
Joined: Thu Oct 24, 2002 10:50 pm
Location: Hungary

Re: Import log for Task import

Post by Zavaros » Tue Jun 09, 2015 3:20 am

Hello,

when you release the task the objects in the task are moved under the header request. Nothing else is done.

the transport file is created when you release the header request. So you can import the transport to other systems only after release of header request.

Regards,

Zav