hi MM experts,
Please advise how to handle this scenario:
I need to create a jumbo capital project PO. It's like a service PO, but once the PO is created and approved, they do not want the amount to be changed.
For example, PO amount is $5,000,000, qty is 1. (We don't know the number of partial invoices to expect)
GR/Service entry needs to be performed for partial invoice.
My issue is when they perform the partial goods receipt, for example for $200k, they have to calculate the percentage for the quantity for the GR as follow:
- GR: amount: 200k, quantity = .04
Is there a better way to handle it without having to calculate the quantity amount for every invoice? Again, the requirement is 1 jumbo PO with unknown # of expected invoice and the PO amount can't be changed once it's approved.
Thanks in advance for your assistance.
Jen