Hello First, thanks for this site, I am a french new user.
I went into COGI to determine some reprocessing records while trying to confirm a prproduction order (Via C011N)
The error message says that "Posting only possible in periods 2012/02 and 2012/01 in company code " and Now we are in april.
I think I should post these records in the right period, but where should I go (CO02?)
Does anyone knows How I could reprocess these records and then solve the error?
Thanks for your help about this point
Best regards
Vince
-
vincedegre
-
- Posts: 10
- Joined: Wed Apr 04, 2012 1:37 am
by vincedegre » Fri Apr 06, 2012 4:13 am
I found the solution
In cogi it is possible to modify the quantity, and to repost by the current period.
Prod order reservation will be deleted after that, and then the prod order can be TECO.
-