Responsible person in the WO operation IW31

Postby VLola » Mon Apr 02, 2012 8:54 am

Dear colleagues.
Tr IW31 There is Work centre and a responsible person for the first operation (header tab ) of word order AFVGD-PERNR . However the responsible person does not exist at the operation tab , only work centre is here.
Is it possible to add the responsible person at the operational level as well . IW41 - confirmation the responsible person also used.
Br
Lola

VLola
 
Posts: 29
Joined: Thu Feb 07, 2008 3:54 am

Re: Responsible person in the WO operation IW31

Postby OrangeStrawberry » Wed Apr 18, 2012 1:22 pm

hi Lola,

I think it depends on how you have the system set-up, you can assign a person to an operation in the Reqmnts Assigment tab under Enhancement in IW31/32 Operations screen.

On my previous engagement we had technicians / engineers created as Business Partners (HR Mini Master was in place), Using MRS the work was schedueld to available resources and each Operation was assigned to a technician/engineer. HR assignment was done for the work centre.

cheers,

OrangeStrawberry
OrangeStrawberry
 
Posts: 8
Joined: Thu Jun 16, 2011 12:58 am

Re: Responsible person in the WO operation IW31

Postby PJA » Thu Apr 19, 2012 2:13 am

1. Go to the Operations tab
2. Double-click on the operation number (e.g. 0010) to drill down to the detail
3. You will now see the Person No on the Internal tab
Pete A
www.pjas.com
PJA
 
Posts: 10884
Joined: Sun Jul 20, 2003 3:11 pm
Location: Deepest darkest Aberdeenshire


Return to Logistics PM

Who is online

Users browsing this forum: No registered users and 6 guests




This website is not affiliated with, sponsored by, or approved by SAP AG.