by Ali123 » Mon Mar 19, 2012 1:03 am
Hi experts,
Here i have a client requirement, we want to transfer material from one plant to another plant
we want to fix material price what ever may be the moving average price
receiving plant receive with fixed price only not depend on moving average price.
i am trying through TRANSFER PRICE concept but still not getting result.
give some lights on this
regards,
Ali
-
Ali123
-
- Posts: 5
- Joined: Tue Mar 13, 2012 7:01 am
by MM888 » Tue Mar 20, 2012 10:44 pm
I think moving a material with MAP control from one plant to another affects the moving average price at the receiving valuation (plant) level.
Have you considered revaluating the material price after the GR to the desired price at the receiving plant?
Try also to explore split valuation if this will address your issue.
Regards,
Ali123 wrote:Hi experts,
Here i have a client requirement, we want to transfer material from one plant to another plant
we want to fix material price what ever may be the moving average price
receiving plant receive with fixed price only not depend on moving average price.
i am trying through TRANSFER PRICE concept but still not getting result.
give some lights on this
regards,
Ali
-
MM888
-
- Posts: 39
- Joined: Fri Mar 09, 2012 9:12 am
by Ali123 » Sat Mar 24, 2012 3:00 am
hi M888,
thanks for ur reply,
what is the concept of """revaluation the material price after the GR tothe desired price"""
can u elaborate the concept with steps.
regards,
Ali
-
Ali123
-
- Posts: 5
- Joined: Tue Mar 13, 2012 7:01 am
by Ali123 » Tue Mar 27, 2012 3:18 am
can anybody explain the concept of transfer price
-
Ali123
-
- Posts: 5