Hi, I've scratched my head a long time about this issue but I thought I'd finally ask someone who might know.
We're basically using MRP-type V2 to make SAP calculate a reorder point using forecasting for materials that we machine from another (raw) material. Lets say it takes 30 working days for us to recieve the raw material (which is MRP-type PD) and then 20 working days for us to make it into the end product. When it comes to the forecasting and reorder point calculation, I want it to consider the 50 days of total replenishment lead time, meaning that we should hit the reorder point 50 days (not counting the safety stock) before we run out of stock. Does anyone know if this is possible and which values to maintain to make it work? We're using forecast model G (moving average) and service level is maintained.
As it is now, we're getting a reorder point that would barely last a month.

