Does anyone have experience with planning calendars in a make-to-order environment?
Have a scenario where we would like to schedule deliveries every Friday ... have defined a planning calendar and lot-sizing routine .. all works well when the material is made or procured to stock
When the material is made to order, it appears that the planning calendar is ignored and the delivery dates are set to match the requirements date, ie. when the reqmts date = Wednesday, the order delivey date is Tuesday [has a 1 day GR time] instead of the preceeding Friday
Is this typical? or have I missed something in the configuration process?