by sabya1411 » Thu Feb 02, 2012 2:55 am
Hi Gurus,
I want maintenance plans to generate 12 call. One call every month.
I am using strategy with 1 MON freq.
I do not want to use Key date...
Because some of the calls are after 28th and there are moved ahead..
If i use "time " only some time more than 1 calls are generated per month.
How is this possible......
waiting for some light..
saby
Thanks & Regards
Saby
Sabyasachi Banerjee
SAP - PM / CS Consultant
-
sabya1411
-
- Posts: 63
- Joined: Fri Jun 09, 2006 1:29 am
-
by PJA » Thu Feb 02, 2012 4:29 am
Saby,
One easy way is to create a factory calendar with the required maintenance days i.e. 1 per month.
You then create a maintenance plan with a 1 DAY frequency.
The drawback with this solution is that you need to keep the factory calendars maintained well into the future.
Pete A
www.pjas.com
-
PJA
-
- Posts: 10884
- Joined: Sun Jul 20, 2003 3:11 pm
- Location: Deepest darkest Aberdeenshire
-
by sabya1411 » Sun Feb 05, 2012 10:03 pm
That will be too much maintenance.
Key date does it quiet well...
Only problem are end of months...
Thanks & Regards
Saby
Sabyasachi Banerjee
SAP - PM / CS Consultant
-
sabya1411
-
- Posts: 63
- Joined: Fri Jun 09, 2006 1:29 am
-
by PJA » Tue Feb 07, 2012 7:07 am
why not create it for the 1st of the following month, but call the orders early??
Pete A
www.pjas.com
-
PJA
-
- Posts: 10884
- Joined: Sun Jul 20, 2003 3:11 pm
- Location: Deepest darkest Aberdeenshire
-
by sabya1411 » Mon Feb 13, 2012 1:24 am
Agree ,..
Planners need to adjust the dates between 1 - 28th of each month.
Thanks for the response Pete.
\
regards
Saby
Thanks & Regards
Saby
Sabyasachi Banerjee
SAP - PM / CS Consultant
-
sabya1411
-
- Posts: 63
- Joined: Fri Jun 09, 2006 1:29 am
-
Return to Logistics PM
Who is online
Users browsing this forum: No registered users and 2 guests