Postby waeb » Wed Dec 24, 2003 10:31 am

Hi all,

I'm working in 4.6c and I got the following problem : the planned independant requirements (VSF) are not consumed by stock transfer orders. It seems to me that stock transfer orders (between plants) are not considered as customers requirements. Is there any way to have planned independent requirements been consumed by stock transfer orders ?

Thank you for your help,
Waeb
waeb
 

Postby Santosh » Sat Dec 27, 2003 6:20 am

Waeb,
It is possible to consume PIRs by stock transport orders/ stock transfer requisitions. Please ensure that while creating PIRs, consumption indicator is 3 and in the MRP3 view of the material master mention mixed mrp indicator 1.
Regards,
Santosh
e-mail: santosh_nsk@yahoo.com
Santosh
Santosh
 
Posts: 50
Joined: Wed Aug 27, 2003 1:42 am
Location: Istanbul, Turkey

Postby Waeb » Mon Jan 05, 2004 5:11 am

Thank you very much, Santosh ! It works fine now ! I forgot to fill the mixed mrp indicator in the material master (view MRP3).

Best regards,
Waeb