If the BOM Header base quantity is changed (with no release key/effective immediately), will the BOM components' quantities automatically recalculate? Or do the corresponding component quantities have to be changed manually?
Thanks for any help you can provide!
Karen
kknolton
 
Posts: 7
Joined: Wed May 23, 2012 10:18 am

Re: If the BOM Header base quantity is changed...

Postby MMPP » Tue Jul 25, 2017 2:41 pm

Hi Karen,

As far as I know, the base quantity and component quantities are independent from each other, so no recalculation of component quantities takes place after updating base quantities in the header.
MMPP
 
Posts: 402
Joined: Tue May 27, 2003 9:42 am
Location: My Desk

Re: If the BOM Header base quantity is changed...

Postby JohnnyB » Wed Aug 16, 2017 5:00 am

Hi Karen

MMPP is of course correct. However, there is a nice feature in CEWB which can assist with this. Let's say you use working area SAP_ITEM and you select all items to be changed. Then select the items as well as column Quantity and choose Extras > Mass Change. Click on the Sum icon ("Enter formulas..."). Here you can enter for example 1.1*x which increases all quantities by 10%. You could even push it further as it allows you to add more sophisticated calculations under "ABAP".

Regards
JohnnyB
JohnnyB
 
Posts: 171
Joined: Tue Apr 12, 2005 8:00 am
Location: South Africa


Return to Logistics PP

Who is online

Users browsing this forum: No registered users and 3 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.