Dispatching Planned Order at Latest Start Date

PostPosted: Mon Mar 06, 2017 2:54 am
by SAPMFGCON
Dear SAPFans,

We tried to dispatch a planned order in CM25 to Basic start date (06-MARCH-2017), but the system dispatch it automatically on the production start date (08-MARCH-2017) considering the scheduling margin key ( 2 days). Is it possible to dispatch it on Basic start date. Even if the date of basic start date is changed to make the the production start date as 06-MARCH-2017 , the system automatically changed the production start date to 08-MARCH-2017 while dispatching.Please advice how to dispatch the planned order on Basic start date. Thanks.