PO main item must be the same as the component?

Postby lalondemt » Tue Sep 23, 2014 1:03 pm

SAPFans,
Attempting to GR 101 a SubCon ("L" category item) PO and we're receiving a "The quantity of the PO main item must be the same as for the component" error.
The BOM for the finished goods being purchased requires different qtys of components (3 per for item two, and 2 per for item 3) and all components were delivered to the PO prior to the GR attempt.
See MIGO screenshot below:
Image
Seems ilogical that it would have to be 1 to 1 components to mains.
What am I missing?
Best,
Mark
lalondemt
 
Posts: 3
Joined: Tue Sep 23, 2014 11:18 am

Re: PO main item must be the same as the component?

Postby Sharpshooter » Thu Sep 25, 2014 1:18 pm

That does not appear to be a standard SAP message. I suspect that your company has created some custom enhancement that is raising this message.

Dave
Good luck!
Sharpshooter
 
Posts: 1171
Joined: Wed Mar 17, 2010 12:01 pm
Location: In the dark

Re: PO main item must be the same as the component?

Postby lalondemt » Thu Sep 25, 2014 1:45 pm

Thanks Dave. I've raised the issue with our team here.
lalondemt
 
Posts: 3
Joined: Tue Sep 23, 2014 11:18 am


Return to Logistics PP

Who is online

Users browsing this forum: Yahoo [Bot] and 1 guest





This website is not affiliated with, sponsored by, or approved by SAP AG.