Postby SAPPP2014 » Thu May 15, 2014 8:58 am

Hello,

I use strategy 40. The situation occurs when a finished product consumes another finished product.
When product A consumes a product B, the planned order should be the sum of quantities A and quantities B.
But this not the case B requirement is minored by A quantity.

Why do I have this problem?
How can I solve this problem?

Thanks in advance
S.