Postby erik0972 » Thu Jul 25, 2013 9:08 am

After releasing a production and confirming and/or partially confirming operations, the order is rescheduled.

The rescheduling appears to switch the dates on the confirmed operations to the actual confirmation date.
I have a requirement that the original schedule date [at lest the schedule date at the time of the confirmation] remain unchanged by the reschedule. The need is to be able to look at 'actual end date' for an operation as set by the confirmation vs the scheduled end data at the time the operation was completed.
Does anyone know of a mean of accomplishing this ? ... so far have tried the 'shift order' indicator on the production order type, tried using a user defined status that 'forbids' reschedule - in both cases the schedule dates either change or actually reschedule.
[hoping for a configuration setting rather than a customized solution to the problem]

Thanks in advance for any feedback/suggestions
erik0972
 
Posts: 137
Joined: Tue Jan 11, 2005 7:50 pm

Re: Reschedule of confirmed operations

Postby JohnnyB » Thu Aug 22, 2013 2:52 am

Hi

I don't think that there is such a config setting. But you could either

1) Implement an enhancmenent to populate the original schedule date into one of the user fields AFVU-USR08 or AFVU-USR09 or
2) You activate the creation of change documents according to SAP note 390635 (which is essentially also an enhancement).

Cheers
JohnnyB
JohnnyB
 
Posts: 171
Joined: Tue Apr 12, 2005 8:00 am
Location: South Africa


Return to Logistics PP

Who is online

Users browsing this forum: No registered users and 5 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.