How to do operation splits in PP-PI

Logistics : PP

Moderators: Snowy, thx4allthefish, Ha Tran

Post Reply
alexdarre
Posts: 80
Joined: Wed Feb 15, 2006 4:29 pm

How to do operation splits in PP-PI

Post by alexdarre » Thu Jun 13, 2013 5:46 pm

I would appreciate if somebody can tell me how to do operation splits in PP-PI, in the same manner that can be done with standard discrete production orders

thanks in advance

Alex Darre

sdonigian
Posts: 3
Joined: Thu Mar 05, 2009 7:40 pm

Re: How to do operation splits in PP-PI

Post by sdonigian » Tue Jun 18, 2013 11:53 am

We had a similar question about a month ago.

From what I could determine from OSS, Google and from an SAP PP Consultant, the Split functionality does not work with Process Orders.
We have kept production order for packaging orders that require splits, and use PPPI for other upstream operations.

I was also told about a function called “order split”, that is part of industry solution (e.g. hi tech or mill solution) but it splits the order as parent and child order which may not be exactly what you are looking for.

Would appreciate it if you share a solution on this thread if you do find a way to do this.

Steve Donigian