Dynamic Work Center Capacity Change?

Logistics : PP

Moderators: Snowy, thx4allthefish, Ha Tran

Dynamic Work Center Capacity Change?

Postby basd » Fri May 17, 2013 7:48 am

Hello all,

I have a requirement which seems to be quite simple and I would like to hear your thoughts and suggestions.

Say, I have a work center and one capacity category, "Person" assigned to it. Within that capacity category, operating time of 16 hours is defined. If I go to CM01, the percentage capacity load is displayed. Simple enough. So, here is the kicker: the requirement is to maintain a different version of operating time, preferably within the same capacity category, in cases where decision is made to add labor and increase operating time from 16 to 24 hours. How can one maintain this data and dynamically toggle between 16 and 24 hour operating time in CM01???

Thanks for your replies in advance!
basd
 
Posts: 117
Joined: Thu Nov 24, 2005 12:08 pm
Location: Cleveland, OH

Re: Dynamic Work Center Capacity Change?

Postby basd » Fri May 17, 2013 12:56 pm

Quick note for those of you who have read the question. Here is the solution: use Available capacity Versions. You can define intervals within each version, specifying shifts and time ranges. When you run Capacity Planning, you can toggle between versions and see the report dynamically change.
basd
 
Posts: 117
Joined: Thu Nov 24, 2005 12:08 pm
Location: Cleveland, OH


Return to Logistics PP

Who is online

Users browsing this forum: No registered users and 5 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.