Postby sek » Mon May 13, 2013 2:25 am

We have 2 types of Make to order processes for which we have 2 BOM structure with Same Material codes of FERT, HALB (subassembly), ROH (components)

First Process (BOM1):
FERT always manufactured in-house.
HALB can be either manufactured in-house or procured thro external subcontracting procurement (Subcontracting PR creation) for which Components transferred to subcontractor


Second Process (BOM2):
FERT always manufactured in-house.
HALB can be always procured thro normal external procurement (Normal PR creation)


Now Sale order created with 2 line items for the same FERT material by the sales personnel.

Production Planner will decide whether we need to manufacture HALB using BOM1 or Procure thro BOM2.

We can activate only the corresponding BOM status and then run MRP for the corresponding sale order item. But this will result every time, planner to change the BOM status.

We need system in such a way that we need to choose the BOM during planned order/production order processing of parent item accordingly it should generate either Subcontracting PR(thro BOM1) or Normal PR(thro BOM2) for HALB item.
Is there any way to achieve this?
sek
 
Posts: 189
Joined: Sun Nov 26, 2006 8:41 am

Re: Make to order

Postby Baisse22 » Fri Jul 12, 2013 7:31 am

You Can achieve this by production versions with different BOM and Routings .
Baisse
Baisse22
 
Posts: 106
Joined: Thu Sep 18, 2003 6:48 am
Location: Germany