work center capacity not utilized in full

Logistics : PP

Moderators: Snowy, thx4allthefish, Ha Tran

work center capacity not utilized in full

Postby Farman » Tue Mar 26, 2013 11:37 am

Dears,

Facing the in the following scenario.
1) Routing defined for the product and Fixed lot size of 60 defined in material master.
2) To manufacture 120 Pcs we need 5.50 hours and our requirement is 1500 pcs, our work center capacity is 7.25 hrs daily.
3) While leveling system don't occupy 7.25 hrs but its occupies 5.5 hours and next lot shifted to next working day.
4) remaining production proposed for next because in remaining hours 7.25 - 5.5 lot of 60 cant be production.

we want to produce as much as we can produce and remaining to be transferred to next day.

Eg. 27 more qty can be produced in 1 day (120+27) so SAP should schedule remaining pcs to next day. how can we do this?

any help would be highly appreciated.

Regards,
FR
Regards,
FR
Farman
 
Posts: 121
Joined: Wed Feb 16, 2005 12:54 am
Location: Pakistan

Return to Logistics PP

Who is online

Users browsing this forum: No registered users and 1 guest





This website is not affiliated with, sponsored by, or approved by SAP AG.