Hi Experts,
I'm running MPS with ' Determination of basic dates for Planned Order' as a background job which works perfectly, now my business users want to ran MPS with 'Lead Time Scheduling' also as a background job but only for specific material numbers in the same plant. What is the best way to run 'MPS with 'Lead Time Scheduling' for specific material no's.
CJ
-
CliffordMcDonald
-
- Posts: 9
- Joined: Tue Aug 19, 2003 10:42 am
by Ramarao » Wed Feb 06, 2013 5:04 pm
MRP group doesn't cover the scheduling option, therefore you need to code it in a user exit. You may still use MRP group as an identifier and when the group = XYZ you can run the MPS job with lead time scheduling. You need this as a separate job step, and then the original job will need to be filtered also (user exit) to exclude these materials - so basically it would be a two step job running some with lead time scheduling and some with basic scheduling.
- Ramarao
-
Ramarao
-
- Posts: 717
- Joined: Wed Dec 11, 2002 7:16 pm
- Location: Dallas, TX
-
Return to Logistics PP
Who is online
Users browsing this forum: Google [Bot], Google Adsense [Bot] and 2 guests