This website is not affiliated with, sponsored by, or approved by SAP AG.

Archive Independent Requirements-Resolved

Logistics : PP

Moderators: Snowy, thx4allthefish, Ha Tran

Archive Independent Requirements-Resolved

Postby 3042517 » Tue Oct 23, 2012 3:04 pm

I'm trying to change the unit of measure for a material but when I display errors after trying to make the change with MM02 it says the UOM can't be changed because Independent Requirements are already assigned to the material. I deleted the independent requirement but still got the error. Next I ran MD74, MD75 and MD76 to delete the old requirments records but I still get the message when I try to change the UOM and I still see history when I run MD73 with display option 3. I had a similar problem because the material had a BOM but I was able to delete and archive the BOM. Is there some similar process to archive independent requirements?
Last edited by 3042517 on Wed Oct 24, 2012 9:31 am, edited 1 time in total.
3042517
 
Posts: 233
Joined: Thu Dec 22, 2005 3:59 pm
Location: The state that started a nation

Re: Archive Independent Requirements-Resolved

Postby 3042517 » Wed Oct 24, 2012 9:31 am

This has been resolved. I'm not sure what I was doing wrong but I retried MD74, 75, 76 this morning and was able to delete the independent requirements history. Perhaps I just need a good nights sleep.
3042517
 
Posts: 233
Joined: Thu Dec 22, 2005 3:59 pm
Location: The state that started a nation