Page 1 of 1

Confirmation labor time depending from machine time

Posted: Tue Oct 16, 2012 9:55 am
by Waebou
Hello,

We have the following process for confirmation :
Activity 2 is the machine time. Activity 3 is the labor time. As the labor time is depending from the machine, we would not like to maintain this time. I created a formula for the cost calculation of the labor time : constant * machine time * operation qty / base qty. This works fine for the budgeted cost in the production order.
But in CO11N this formula is not taken into account and the labor time is not updated by the confirmed machine time.

Does anyone have the same problem ? How to resolve this issue ? Is there any user exit to update labor time depending from the machine time ?

Thanks in advance for your help.

Waebou

Re: Confirmation labor time depending from machine time

Posted: Wed Oct 31, 2012 9:26 am
by ESCOCES
Hi,

Check on Work Center, into slot 2 control key.