No Planning File Entry After Routing Change (repost/2005)

Logistics : PP

Moderators: Snowy, thx4allthefish, Ha Tran

No Planning File Entry After Routing Change (repost/2005)

Postby CKVDK » Fri Sep 14, 2012 4:15 am

Hi all,

Changes in routing will affect the leadtime of the operations. This change causes the start date of the planned order to shift in or out from the original start date. The change in start date will also change the requirement date for the materials.

Since no planning file entry has been created, MRP will not run on the assembly, therefore, the updated routing is not taken into account and the start date of the planned order is not changed.

Has anybody come across a situation like this? If so, how have you resolved it. The SAP solution is to manually create a planning file entry but we don't want to do this.

CKV.
CKVDK
 
Posts: 1
Joined: Fri Sep 14, 2012 3:27 am

Return to Logistics PP

Who is online

Users browsing this forum: Yahoo [Bot] and 4 guests





This website is not affiliated with, sponsored by, or approved by SAP AG.