MPS run ignored MPS material

Logistics : PP

Moderators: Snowy, thx4allthefish, Ha Tran

Post Reply
ollkk
Posts: 60
Joined: Thu Dec 31, 2009 3:31 am

MPS run ignored MPS material

Post by ollkk » Fri Feb 10, 2012 5:51 am

Hello

I have a material marked with an MPS MRP type and has planned independent requirements all visible on MD04.

when the nightly MPS job ran, it didn't create any planned orders for the PIRs for this material.

My MPS settings are:
Processing key NEUPL Regenerative planning
Create purchase req. 3 Planned orders
Schedule lines 3 Schedule lines
Create MRP list 1 MRP list
Planning mode 3 Delete and recreate planning dat
Scheduling 1 Basic dates will be determined


any ideas? the material master settings look fine.
Thanks,

Oll

Ramarao
Posts: 717
Joined: Wed Dec 11, 2002 7:16 pm
Location: Dallas, TX
Contact:

Re: MPS run ignored MPS material

Post by Ramarao » Fri Feb 10, 2012 9:48 am

Do you see the PIR itself in MD04? What strategy group are you using.
- Ramarao

ollkk
Posts: 60
Joined: Thu Dec 31, 2009 3:31 am

Re: MPS run ignored MPS material

Post by ollkk » Fri Feb 10, 2012 9:55 am

Yes I can see the PIRs in MD04. There is no strategy group on the material other than the MRP type is m3 so standard MPS.
Thanks,

Oll

Ramarao
Posts: 717
Joined: Wed Dec 11, 2002 7:16 pm
Location: Dallas, TX
Contact:

Re: MPS run ignored MPS material

Post by Ramarao » Fri Feb 10, 2012 2:33 pm

I am not sure you could enter a PIR without a strategy group?

And, if M3, what's your planning time fence, and when is your requirement date?
- Ramarao