Postby doit » Tue Jul 26, 2011 8:10 am

Dear Experts,

We use alternative item in bom and using the strategy 2(100% check), sometimes we wants to use the secondary item in particular order. could someone tell me how to change the alternative strategy in planned order? if the strategy not be changed, the alternative relation will be updated after ATP check for the planned order.