BOM item assignment to multiple operations

Logistics : PP

Moderators: Snowy, thx4allthefish, Ha Tran

Post Reply
vaditya10
Posts: 89
Joined: Fri May 23, 2003 12:03 am
Location: India-New Delhi

BOM item assignment to multiple operations

Post by vaditya10 » Fri May 06, 2011 2:22 pm

Team
We have situation where BOM item is used at more then one operation/phase i.e Item 10 of a BOM having qty 100 is used at operation/phase 10 with qty 30
Operation/phase 20 as qty 40 and operation/phase 40 as qty 30.

How to do that?

Is there any std way where we can split the qty while doing component assignment at Recipe?

Ramarao
Posts: 717
Joined: Wed Dec 11, 2002 7:16 pm
Location: Dallas, TX
Contact:

Re: BOM item assignment to multiple operations

Post by Ramarao » Tue May 10, 2011 9:22 am

Standard solution is to create two different BOM items with split quantities and assign them to different operations/phases.
- Ramarao