MC8G Transfer Problem

Logistics : PP

Moderators: Snowy, thx4allthefish, Ha Tran

MC8G Transfer Problem

Postby srwpchelp » Thu Nov 05, 2009 5:37 am

Hi,

Every month I have to transfer the new forecast data from Flexible Planning into Demand Management using MC8G.
New items sometime fail to transfer correctly (e.g. because I haven't set up the data correctly).

How can I see a list of items that have failed to transfer correctly?

Thanks.
srwpchelp
 
Posts: 23
Joined: Fri Mar 20, 2009 3:09 am

Re: MC8G Transfer Problem

Postby srwpchelp » Fri Nov 23, 2012 5:29 am

Hi,

I am still having problems in transferring the forecast for new items into Demand Management using MC8G.

Here's what I do :-

1. MC8E - enter the Job Number and reset the status.
2. MC8E - enter the job number and add the new items to the existing list of materials. The Sales Org, Dist Channel, Division and Plant details are hard-coded into the Job Number.
3. MC8G - enter the Job number and run the background job "immediately".

Sometimes it works, sometimes it doesn't.
Once it works for a new item then it always works for that item.

Any help would be greatly appreciated.
srwpchelp
 
Posts: 23
Joined: Fri Mar 20, 2009 3:09 am


Return to Logistics PP

Who is online

Users browsing this forum: Yahoo [Bot] and 1 guest





This website is not affiliated with, sponsored by, or approved by SAP AG.