Postby autobots123 » Tue Jul 10, 2012 1:19 am

Material X has been updated with 3 mth planned qty via MD61. Later Material Y has been updated in different screen of MD61, but the qty has been copied over to PIR Material X. Although changes has been done, it keeps following either of this material's PIR. There's no linkage between this material.
Really appreciate if anyone can help on this :).

autobots123
 
Posts: 7
Joined: Tue Jul 10, 2012 12:52 am

Re: Planned Independent Requirement overwrites another material

Postby autobots123 » Tue Jul 31, 2012 10:16 pm

Issue has been resolved
These materials are sharing the same requirement pointer(can be seen in table PBIM).The planned qty and change history will be updated in other tables eg: PBED and PBHI referring to the same key requirement point # in PBIM. Whenever there are changes of planned qty for this material, system will refers to this requirement point # and update PBHI and PBED accordingly.

use Transactions MD74-->MD76 :will delete the whole details/history on the materials. After the 3 transactions have been executed, the new MD61 for the material will create new unique requirement point #.
autobots123
 
Posts: 7
Joined: Tue Jul 10, 2012 12:52 am

Re: Planned Independent Requirement overwrites another material

Postby Ramarao » Wed Aug 01, 2012 11:19 am

Interesting. But based on your system version, it could be related to the material status as well.. Please check OSS note # 1006619
- Ramarao
Ramarao
 
Posts: 694
Joined: Wed Dec 11, 2002 7:16 pm
Location: Dallas, TX


Return to Logistics PP

Who is online

Users browsing this forum: No registered users and 4 guests




This website is not affiliated with, sponsored by, or approved by SAP AG.