Postby Guest1 » Wed Dec 04, 2002 12:17 pm

Hello All :

In 31H system, when we use to allocated material to network, system use to create one P.req and increase line items as we attached more materials to different activities of the same network.

We have moved to 46B now. In our current system, SAP generates new P.Req for each material line.

Any idea, where I can make config changes so that system keeps same Req number for one network. There is always one Reservation number but P.Req number keeps on changing.

Thanks in advance

Pete
Guest1
 

Postby Guillermo » Wed Dec 04, 2002 2:08 pm

Hi

Revise the transaction OPUV and verify if the check box "CollctveRequstn" is checked, you need verify this indicator for each plant that you have customized.

Regards
Guillermo
 
Posts: 39
Joined: Fri Nov 15, 2002 2:05 pm
Location: México


Return to Logistics PS

Who is online

Users browsing this forum: No registered users and 3 guests





This website is not affiliated with, sponsored by, or approved by SAP AG.