Pl. list MM-PS integration areas...

PostPosted: Wed Dec 04, 2002 6:27 am
by suresap
Hi All,

I am a MM consultant and am trying to explore the integration areas in PS. Can someone of u pl. help in listing the MM-PS intergrations, so that I can learn only that part of PS topics (and of course necessary topic thereof like masters, org. structure)

Thanks in advance.

PostPosted: Thu Dec 05, 2002 1:21 am
by Bobo
Material item can be assigned to an activity in a project as component. This assignment triggers the creation of reservation/PR in MM. Just like assigning a material to BOM, you also have to specify the quantity needed and the requirement date, if a material is to be backflush, if it is a bulk material.

Thanks BoBo

PostPosted: Tue Dec 10, 2002 1:50 am
by suresap
Thanks Bobo

PostPosted: Tue Dec 17, 2002 8:02 am
by Saphir
Network activities of type 'external processing' can automatically generate purchase requisitions. That is, for sub-contracting or external service procurement (consulting etc.). All the purchasing data can be determined via info records which are inserted in o.m. activities.