Scheduling while Copying

Postby sappsfan » Sun Dec 01, 2002 10:43 pm

Hi All,

I have maintained no automatic scheduling in my WBS Scheduling profile and Overall network scheduling profile. I have also not given any past date in the scheduling profile.

However when I am including a entire structure (Std WBS and Networks) , the system automaticaly schedules the included project.

Where can I control this scheduling ?

Regards,
SAPPSFan
sappsfan
 

Reply

Postby Anthony_Radford » Mon Dec 02, 2002 10:36 am

Hi,

Scheduling is always carried on the creation of a Project or Network regardless, of how it is created. This is as per design and is required for other functionality.
Kind Regards,
Anthony Radford
e-mail: anthony.radford@SAP.com
Anthony_Radford
 
Posts: 3
Joined: Mon Dec 02, 2002 10:31 am


Return to Logistics PS

Who is online

Users browsing this forum: No registered users and 3 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.