Restricting levels in a WBS

Logistics : PS

Moderators: Snowy, thx4allthefish

Restricting levels in a WBS

Postby mobpd » Thu Nov 28, 2002 5:06 am

hi

we only require projects with one level 1 and then several level 2. Is there a way of limiting operative WBS to a maximum of level 2 (ie no level 3 and below can be created)

Thanks
mobpd
mobpd
 

Postby Anthony_Radford » Mon Dec 02, 2002 11:08 am

Hi,

You could try creating a WBS validation wich checks the WBS element level being created and then raises an error message if it is greater than 2. This you can then set in you project profile.
Kind Regards,
Anthony Radford