Postby Cristina Teixeira » Tue Nov 26, 2002 1:33 pm

Hi,

Is there any way of scheduling (planning dates), simultaneously, several networks associated to different projects (different PEP definitions), in the same planning board ?
Our customer is using ARTÉMIS to do this, but he wants to do the same thing with SAP.

TIA,

Cristina
Cristina Teixeira
 

Postby Guest » Thu Dec 05, 2002 4:59 pm

You can use the Overall network scheduling, If they linked to each other then you can use the overall network scheduling. If not try to see if the mass change functionality works for you or not. With this you can schedule many networks but not in the planning board.
Guest
 