PS for fixed assets monitoringWe are looking into using PS for fixed assets monitoring by producing variance report on budgeted amount and the actual acquisition cost at line item level. Could anyone advise me how to go about it briefly or recommend me documentation where I can find details. I have been searching through the help facility.
Thanks for any help.
Hi
1) Create a statistical WBS element. 2) Create the budget and release it. 3) Link the asset and the WBS element (AS02 / Master Data / Time-dependent). 4) From this moment you can follow up the asset costs using the PS funcionalities. 5) Remember that the costs continue being allocated to the asset. Good luck.