Postby x » Wed Nov 20, 2002 7:09 pm

I have included a substitution rule for getting the cost center while executing CJZ1/CJZ2 - this works fine , however if I reverse for CJZ1/CJZ2 it ignores the cost center on the document it is reversing and goes to the OKB9 (default cost center table) table.

This is wrong - has anyone encountered this issue and came up with a solution