Enter work remaining to complete activity

Logistics : PS

Moderators: Snowy, thx4allthefish

Enter work remaining to complete activity

Postby Csaba » Wed Nov 20, 2002 4:03 am

Half way through the project the project engineer would like to enter work he believes remains to do until completion.
E.g. 100 hours of work were planned for the activity in the network in which a construction is to be made. When the construction is half made and say already 80 hours have been posted to the activity, the project engineer estimates that still 40 hours of work must be done before the construction is finished. He wants to enter this 40 hours somewhere. How can he do that? He does not want to modify the original plan of 100 hours to 120 hours!
If you know how to do it, please let me know.
Thanks, Csaba
Csaba
 
Posts: 41
Joined: Mon Oct 21, 2002 10:57 am
Location: Hungary

Postby didier » Wed Nov 20, 2002 7:21 am

hello Csaba,

in the confirmation of hours on a netwurk, there's a field 'remaining work ' available.

Just use transaction CN25.

regards. Didier
didier
 