Run MRP for project

Logistics : PS

Moderators: Snowy, thx4allthefish

Run MRP for project

Postby Guest » Sat Nov 09, 2002 1:45 am

When I run MRP for project, the system just concerns the project stock, does not involve all the stock in the plant, why? Can I Run MRP for project involve all the storagelocation? thanks
Guest
 

Postby megasanju » Tue Nov 19, 2002 1:22 am

The MRP for Project plans all the materials in the relevant project stock. This is because the materials in the project stock are restricted to the project use only. But when u run the MRP at plant level then the materials in the unrestricted use (plant stock) as well as materials in the restricted use (project) are planned.

MRP for project will plan only materials for the project stock. Run MD01/MD02 if u want to plant plan the materials even at storage location level.
megasanju
 