I realize I am probably getting ready to ask a dumb question so my apologies up front.

We use SAP and I am trying to find a way to pull a report shows the following in regards to staff overhead time/labor charging:

• The Date the time was charged
• The amount of time that was charged on that date
• The total amount charged in USD for that time on that date

I was told to pull a CJI3 report, but it is not providing what I need in regards to the layout I am using.

Just to clarify, I use SAP Logon 730, click on P12 ONE, login, type in CJI3 and my project info and pull the report.

Any help is appreciated.

Re: Labor Report

PostPosted: Mon Mar 09, 2015 5:09 am
by Gothmog
Moved from General Discussion