CNMASS chnges

PostPosted: Wed Nov 12, 2014 12:02 am
by unurd
Hi,

I wish to fill out Actual Finish Date in some WBSs together and overide validations I defined.

I ran CNMASS on a particular WBS, but I see it changed also the date in the above WBSs, e.g.:
Want to change on: P-00010.05.01.05.
The system changed also in P-00010.05.01

I expect it to change only the WBS I chose, I would also understand if it changed down, e.g.
P-00010.05.01.05.01, but up???? Why? Can I overide it?

Tried also to run this sequence :

BAPI_PS_INITIALIZATION
BAPI_BUS2054_CHANGE_MULTI
BAPI_PS_PRECOMMIT
BAPI_TRANSACTION_COMMIT

but it falls in validation.

Any suggestions?

Thanks, Amos.