Fill actual finish date of the WBS element

PostPosted: Mon Sep 15, 2014 11:44 pm
by unurd
Hi,

After release of a WBS, I wish to fill Actual finish date of the WBS element (field PRTE-IENDE).
I get error message no. CJ512:
Diagnosis
You cannot enter any actual finish dates for WBS element XXXX if:
• The subordinate WBS element does not have an actual finish date.
• Or the activities in the WBS element do not all have final confirmations.
I don't have subordinate WBS, but I do have network & activities.
If I confirm everything, I can fill the date.
My problem is that the activities are not engineering but financial, and a lot of them. They don't have to be confirmed. To confirm each activity is not applicable.
Any suggestion what I can do?

Thanks, Amos.