Hi Experts,

I am attempting to build a report that would mimic PO creation process for my client. My issue is that I am unable to find where the conditions are determined for each component being added into the project when CN33 is being run.

After each component is added through CN33, the component has the same price as the PO will eventually have, where do PS determine this price?

Thanks!
andrewmcgrath
 